Gantt View: Activate Dependencies and use Predecessors (2024)

Use the Dependencies functionality in Smartsheet, to automatically calculate and adjust dates as values for Duration and Predecessors change.

PLANS

For more information about plan types and included capabilities, see the Smartsheet Plans page.

Permissions

The sheet's Owner andAdmins can modify the sheet Project Settings.

Find out if this capability is included in Smartsheet Regions or Smartsheet Gov.

When you activate Dependencies, your sheet has the following functionality:

  • Changes in the start or end date on the predecessor immediately adjust the dates of its dependents.
  • Changes in two of the Start Date, End Date, and Duration columns automatically calculate the third value.
  • Start Date, End Date, Duration, and % Complete roll up to parent rows as summary calculations.
  • Parent row values are read-only, as they’re calculated automatically based on values in the child rows.
  • You can highlight the critical path in the Gantt chart to visualize what drives the overall project duration.

Take into consideration that when you activate dependencies, you can't use formulas in theStart Date, End Date, Duration, % Complete, andPredecessors columns.

Activate or deactivate Dependencies

  1. Right-click any column header in the Gantt chart and selectProject Settings.
  2. Select the Dependencies enabled checkbox.

    Gantt View: Activate Dependencies and use Predecessors (1)

  3. Select which columns to use as the Predecessor column and the Duration column.

    If you don't have columns set up for this, Smartsheetautomatically creates the Predecessorsand Durationcolumns.

  4. Select OK.

To stop using dependencies and remove the automation from the sheet:

  1. Right-click any column header in the Gantt chart and selectProject Settings.
  2. Uncheck the Dependencies enabled box.
  3. SelectOK.

Duration and Predecessors

When you enter a duration or predecessor value in a row, the Start Date and End Date populate automatically based on the working days schedule established in the Project Settings.

Duration

Duration is the amount of working time between the start and end dates. The system automatically calculates duration based on a start and end date, or you can manually enter it in the Duration column.

When calculated automatically, your duration is returned in days. For other units, enter Duration manually.

You can use different formats, for example:

  • Weeks: 2w
  • Whole working days: 4d
  • Partial working days: 3.5d
  • Hours: 7h
  • Minutes: 60m
  • Seconds: 500s
  • Milliseconds: 50000ms
  • A combination of hours, minutes, seconds, and milliseconds: 4h 30m

A duration of zero creates a diamond shape on the Gantt chart, indicating amilestone: a significant event or checkpoint.

Elapsed time can be used in theDuration column to ignore nonworking time (including nonworking days and holidays). Lead with an “e” to indicate duration in elapsed time, for example: e3d, e5h.

Consider the following when working with theDurationcolumn:

  • Parent rows always reflect duration in partial working days.
  • If your task takes longer than anticipated, you can increase the duration to push out the end date. This also pushes out the end dates of any dependent tasks automatically.
  • When you provide a duration and a start date, the dependency functionality calculates the end date automatically by adding the number in theDuration cell to the start date, excluding any nonworking days.
  • If using partial working days, Smartsheet considers the length of working days when calculating the end date.
  • You can manually schedule a task to start on a nonworking day. When doing so, the start date is included in the duration, but it excludes subsequent nonworking days.

Predecessors

You canmake a task dependent on another task by typing another row's number in itsPredecessor column. The date of the dependent task automatically adjusts as the predecessor tasks dates change.

The task dependencies that you create drive theproject's critical path. With task dependencies, Smartsheet determines the sequence of tasks that drive the duration of the overall project.

To define predecessors:

  1. Find the row for which you want to create a predecessor.
  2. In the Predecessor column, type the row number for the item that must occur first.

You can add multiple predecessors by entering the row numbers into the cell and separating them by a comma.

Adding predecessors to a parent row in a hierarchy applies the predecessor to all of its child rows due to the parent roll-up functionality. This predecessor relationship prevents direct changes in the dates in child rows. To work around this, set predecessors at the lowest-level child rows whenever possible.

Consider the following:

  • If a predecessor drives a task's start or end date, you can change it manually by clicking the cell and selecting a new date. Doing so overrides the association with the predecessor and removes the value from the row.
  • If a parent row has a predecessor value listed, this dependency relationship drives the start dates for each child row. Removing the predecessor value on the parent row makes child rows editable for you to change dates manually.

Edit a predecessor relationship

By default, when you specify a predecessor, a Finish-to-Start relationship is established between items, but you can change that.

Use theLagfield to represent a period of inactivity or overlap between the predecessor and dependent.

For instance, entering 1d into theLag field for aFinish-to-Start dependency causes the dependents to start a working day after its predecessor finishes.

To schedule the dependents to start before the predecessor finishes, use a negative number (for example, -1d) to create lead time.

  1. Select Gantt View: Activate Dependencies and use Predecessors (2) Edit Predecessors, located at the right of any Predecessors cell in the column.
  2. Select the relationship type:
  • Finish-to-Start (FS): Start after the predecessor finishes.
  • Finish-to-Finish (FF):Finish at the same time that the predecessor finishes.
  • Start-to-Start (SS): Start at the same time that the predecessor starts.
  • Start-to-Finish (SF):Finish before the predecessor starts.
  1. Select aLagtime. You can enter weeks, whole working days, partial working days, hours, minutes, seconds, milliseconds, or a combination (in similar fashion to the Duration examples).
  2. SelectOK.
Gantt View: Activate Dependencies and use Predecessors (2024)

References

Top Articles
Latest Posts
Article information

Author: Edwin Metz

Last Updated:

Views: 6003

Rating: 4.8 / 5 (78 voted)

Reviews: 85% of readers found this page helpful

Author information

Name: Edwin Metz

Birthday: 1997-04-16

Address: 51593 Leanne Light, Kuphalmouth, DE 50012-5183

Phone: +639107620957

Job: Corporate Banking Technician

Hobby: Reading, scrapbook, role-playing games, Fishing, Fishing, Scuba diving, Beekeeping

Introduction: My name is Edwin Metz, I am a fair, energetic, helpful, brave, outstanding, nice, helpful person who loves writing and wants to share my knowledge and understanding with you.